Inspection Models Considering the Overlapping of Inspection Span and Failure Downtime

ZHANG Xingfu, CHEN Maoyin, ZHOU Donghua   

  1. Tsinghua National Laboratory for Information Science and Technology, Department of Automation, Tsinghua University, Beijing 100084, China
  • Received:2012-05-08 Revised:2012-07-16 Online:2012-12-28 Published:2012-12-28

Inspection Models Considering the Overlapping of Inspection Span and Failure Downtime

张幸福, 陈茂银, 周东华   

  1. Tsinghua National Laboratory for Information Science and Technology, Department of Automation, Tsinghua University, Beijing 100084, China
  • 通讯作者: CHEN Maoyin,E-mail:mychen@mail.tsinghua.edu.cn

Abstract: In the literature,many works on determining inspection interval by the delay time concept generally assumed that the time of inspection span and the time of failure renewal are negligible.However,in realistic cases,the above time should not be neglected for both the time itself and its effect.In order to model the effect of the possible overlapping of inspection span with failure downtime on determining the optimal inspection interval,we propose a block-based inspection model for a single component-based on delay time concept.We further compare this model with the age-based model to show the practical sense.The developed models are also demonstrated by numerical examples.

Key words: block based inspection, delay time concept, inspection schedule, maintenance

摘要: In the literature,many works on determining inspection interval by the delay time concept generally assumed that the time of inspection span and the time of failure renewal are negligible.However,in realistic cases,the above time should not be neglected for both the time itself and its effect.In order to model the effect of the possible overlapping of inspection span with failure downtime on determining the optimal inspection interval,we propose a block-based inspection model for a single component-based on delay time concept.We further compare this model with the age-based model to show the practical sense.The developed models are also demonstrated by numerical examples.

关键词: block based inspection, delay time concept, inspection schedule, maintenance